26 de September de 2024

ROMERO POLO EXECUTES THE WORK ON THE MODULES OF THE ARNAU HOSPITAL IN LLEIDA

Romero Polo has installed a prefabricated, modular and demountable building in the Arnau hospital square in Lleida, which will remain in place for two years. The aim of the project is to temporarily relocate the consultations and services that were offered in the surgical block of the center, which is currently under construction.

The contract for these new modules requires a usable area of no less than 1,000 square meters. Thus, the building is expected to have sixteen outpatients’ offices and four offices (two for radiological protection and two for electromedicine), in addition to the Neurology day hospital and other auxiliary areas for healthcare personnel. The project has a total budget of 2,845,920 euros and will be executed in collaboration with Acsa Sorigué.